So the waiting list of companies with wide-ranging applications is steadily increasing. Bronsima: “There are currently 250 companies in Drenthe on the waiting list with plans to purchase additional electricity, and twice as many entrepreneurs with requests to provide sustainable electricity. Unfortunately, we cannot deal with that now.”
According to her, it is difficult to say how long companies will have to wait until space is available on the network again. “It depends very much on the location and how quickly we get additional space through the measures. It could take a year, but it's also longer.” Due to problems in the network, entrepreneurs are currently unable to become more sustainable or expand.
At present, the power grid is still tight. Berends: “With all the investment plans in place now, the situation will improve in the long term, but the newly planned power plants will not be installed overnight. On average, this takes six to eight years per site, depending on procedures, building materials and manpower.” And any objections.”
That is why the motto of grid operators is, in addition to now focusing on strengthening the grid, also the smart and efficient use of electricity. Bronsema: “Of course, individuals can also do this, for example by essentially using electricity when you generate it yourself using solar panels.”
Currently, these are non-binding tips for consumers and businesses to deal smartly with energy stress. Berends: “But I can imagine that we will eventually have to direct more to accelerate this change in behavior. Moreover, we are calling for some kind of crisis and recovery law for the construction of new power plants, to accelerate as much as possible.” Blocking.”
Avid music fanatic. Communicator. Social media expert. Award-winning bacon scholar. Alcohol fan.